Update of the timetable of the Czech-Norwegian research program call is mainly brought about by the emphasis on quality, objective and impartial evaluation of the large number of submitted applications. There were 389 proposals submitted in the call, to the next stage of assessment total of 383 project proposals progressed. For evaluation of the proposals the Ministry of Education, Youth and Sports engage mainly foreign experts.
Evaluation Period, the period during which the project proposals are evaluated in accordance with the Guidelines for Evaluators, the Programme Operator decides and announces the results of the Call, it takes a maximum of 240 calendar days. |
4 February, 2014 – 14 July, 2014, 2014 (161 calendar days) |
Announcement of the Results of the Call on the website of the Programme Operator. As of this day the applicants are provided with the results of the Call, including justification and the information of the evaluation of their project proposal/s without specification of any personal data of relevant opponents. |
15 July, 2014 |
Record of Public Tenders in Research, Development and Innovation (VES): Provisions of data on the evaluation of the Call by Programme Operator - within 50 calendar days from the date of publication of the results of the Call. |
3 September, 2014 at the latest |
Expected Date of Project Contract Signature - no later than 60 calendar days from the date of entry into force of the Law on State Budget for 2014 or of the date of the announcement of the results of the Call when the result was announced after the effective date of this Act. |
13 September, 2014 at the latest |
Central Register of Research, Development and Innovation (CEP): The Programme Operator provides the applicable data on projects funded from the state budget, within 50 calendar days of the effective date of enforceability of the project contract. |
1 November, 2014 at the latest |
Deadline for the Provision of the Grant: The Programme Operator is obliged to start providing support for up to 60 calendar days from the effective date of enforceability of the project contract. |
1 November 2014, at the latest |